• Welding and installation of Ø 34-inch and 48-inch steel casing pipe then insertion of DN600 and 800 mm GRP carrier pipes. -
-
-
Project Facts:
- This is the first time MT technique was applied in the KAEC.
- The main contractor has requested STCC to construct stormwater as a matter of urgency because of
Water collection near the neigh borhoods were extremely dangerous. - The drainage channel (Wadi) was constructed. Thus, starting and ending points were very specific and
in most crossing ground cover depth was not complying with the minimum requirement of MT works
Critical Success Factors:
- Obtained prequalification from the Client/EMAAR & (HDR INC) consultant, all required documents and credentials had been submitted as per requirement, STCC was the first tunneling company that executed the trenchless work in the city.
- Provided a suitable team of well-experienced staff.
- Took extreme precautions to monitor the ground movement.
- STCC had completed its scope of work to the utmost level of satisfaction for both customer and end Client/ EMAAR represented by (HDR INC) consultant.